List all online project management dependencies using the following table:

Activity Depends on Dependency Type
Setup Project Office Appoint Project Team Finish-to-Finish

Project Planning: Project Dependencies Table

In the example given above, the activity ”Appoint Project Team” must finish before activity “Setup Project Office” can finish.

Assumptions

Identify any planning assumptions made during this planning process. For example, it may be assumed that:

  • · The project will not change in scope
  • · The resources identified will be available upon request
  • · Approved funding will be available upon request.

Constraints

Identify any planning constraints identified. For example:

  • · The project team must create all project deliverables using the approved funding, resources, materials and equipment only
  • · The project team must create all project deliverables within normal working hours only.

You are now ready to collate all of the materials listed in this section and create your Project Plan document. This document forms the basis upon which the project is measured and it will be referred to throughout the Project Lifecycle. The next step in the project Lifecycle is to create a Resource Plan.